Street Rehab Underway in Seven Neighborhoods

7/12/2016

0 Comments

 
Picture
For Immediate Release
Monday, July 11, 2016
Media Contact: Ursula Miller
ursula.miller@cincinnati-oh.gov
513-352-3417
 
CINCINNATI – Crews have begun $7.6 million in extensive repairs to 44 streets in Kennedy Heights, Madisonville, Pleasant Ridge, Avondale, North Avondale, Corryville and Evanston.

The work, which includes grinding off existing roadway surfaces, full-depth repairs and a new surface layer of pavement, is funded as part of the city’s Capital Acceleration Plan. The rehab portion of CAP totals $9.9 million this year, covering eight neighborhoods, 50 streets and 37 lane miles of improvements.

​Another $2.3 million in rehabilitation on six streets has begun in Northside, starting this week with Spring Grove Avenue at Elmore Street to Crawford Avenue. 

Most of the major, full-depth repairs in Kennedy Heights, Madisonville, Pleasant Ridge, Avondale, North Avondale, Corryville and Evanston have been made. Reconstruction of Highland Avenue near the Lester Road intersection in Pleasant Ridge was completed last week and has been reopened. Crews are now grinding and leveling streets.

Please see below for a complete list of streets scheduled for rehabilitation this summer.
The type of work varies based on the condition of each street but generally includes:
  • Grinding and paving
  • Replacing curbs and curb ramps
  • Repairing driveway aprons and sidewalks, as required
  • Adjusting utility castings to grade
  • Final surface coat of new pavement
  • Line striping
Typical work hours are 7:00 a.m. to 6:00 p.m. Monday through Friday. Crews may work later into the evening and on Saturdays, if needed.
Rehab work takes about two months to complete per street. On most streets, at least two lanes will remain open to through traffic during repairs. Local access to residences and businesses will be available at all times.
 
All roads will be reopened to through traffic during non-work hours.

On-street parking may be prohibited, as needed, to accommodate crews. Signs will be posted in advance to allow motorists time to find alternate parking options. In most cases, these temporary restrictions will be in place for less than 24 hours and a street will be reopened by 6:00 p.m. Violators will be towed per city ordinance. 
 
All work is expected to be complete by Dec. 1. Look for updates throughout the summer.
For questions about the project, contact Dave Krusling, Senior Engineer, Department of Transportation, at 513-352-3479 or dave.krusling@cincinnati-oh.gov.

About the Capital Acceleration Plan (CAP)
The Capital Acceleration Plan is improving streets and City owned vehicles to eliminate long-term maintenance and repairs costs. In terms of city streets, CAP provides $69 million in additional funding for improvements over the next six years. Combined with the annual street improvement program, outside grants and CAP, Cincinnati is investing approximately $172 million to rehabilitate or resurface more than half its 2,936 total lane miles in all 52 neighborhoods by June 30, 2021. This investment will improve safety, save money, enhance the city’s business environment and raise the overall quality of life for residents.
For more information, please visit http://cincinnati-oh.gov/manager/capital-acceleration-plan-cap/
 
 
Cincinnati Streets Scheduled for Rehabilitation in Summer 2016
 
Kennedy Heights, Madisonville and Pleasant Ridge (All roads to be finished by Aug. 31)

  • Carpathia Street from East Terminus to Lester Road
  • Cypress Way from South Terminus  to Montgomery Road
  • Davenant Avenue from East Terminus  to Kinoll Avenue
  • Fairway Drive from Montgomery Road  to Langdon Farm Road
  • Highland Drive from Lester Road  to Corporation Line
  • Hurd Avenue from Plainville Road  to West Terminus
  • Iberis Avenue from Hedge Avenue  to Red Bank Road
  • Indian Mound Avenue from Corporation Line  to Cypress Way
  • Islington Avenue from Watterson Street  to La Crosse Avenue
  • Kincaid Lane from South Terminus  to Kincaid Road
  • La Crosse Avenue from Murray Road  to North Terminus
  • Mapleleaf Avenue from Ridge Avenue  to Lester Road
  • Marmion Lane from South Terminus  to Douglas Terrace
  • McHugh Place from South Terminus  to Montgomery Road
  • Onondago Avenue from Davenant Avenue  to Congreve Avenue
  • Rex Avenue from South Terminus  to Islington Avenue
  • Solar Vista Place from East Terminus  to Kennedy Avenue
  • Valleyview Avenue from Davenant Avenue  to Aikenside Avenue
  • Verulam Avenue from South Terminus  to Auten Avenue
  • Vinewood Avenue from Corporation Line  to Plainville Road
  • Wiehe Road from Langdon Farm Road  to Corporation Line
 
 
Avondale, Corryville, Evanston and North Avondale (All roads to be finished by Aug. 31)


  • Alaska Court From Glenwood Avenue to North Terminus
  • Bonaparte Avenue From Hewitt Avenue to Huron Avenue
  • Burnet Avenue From William H Taft Road to Forest Avenue
  • Debbe Lane Reading Road to North Terminus
  • Dickson Avenue From Clinton Springs Avenue to Mitchell Avenue
  • Durrell Avenue From Victory Parkway to Gilbert Avenue
  • Forest Avenue From Reading Road Dury Avenue
  • Glencross Avenue From Wedgewood Avenue to Mitchell Avenue
  • Graydon Avenue From Hewitt Avenue to Huron Avenue
  • Hickman Avenue From Reading Road to Harvey Avenue
  • Hickory Street From Knott Street to West Terminus
  • Holloway Avenue From Fairfield Avenue to Montgomery Road
  • Holloway Court From South Terminus to Holloway Avenue
  • Huron Avenue From Bonaparte Avenue to Fairfield Avenue
  • Knott Street From Maple Avenue to Rockdale Avenue
  • Lenox Lane From South Terminus to Redway Avenue
  • Maple Avenue From Reading Road to Harvey Avenue
  • Marion Avenue From Winding Way to North Terminus
  • Red Bud Place From Red Bud Avenue to Rose Hill Avenue
  • Spokane Avenue From Hewitt Avenue to Huron Avenue
  • Vernon Place From Oak Street to Martin Luther King Jr. Drive
  • Vernon Place From Vernon Place to North Terminus
  • Vine Vista Place From Clinton Springs Avenue to North Terminus
  • Warwick  Avenue From Clinton Springs Avenue to Mitchell Avenue
 
Northside (All roads start in late July, except where noted. Work scheduled to be finished by Dec. 1.)


  • Cosby Street From Spring Grove Avenue to Hamilton Avenue
  • Mad Anthony Street From William P Dooley By Pass to Spring Grove Avenue
  • North Argyle Place From South Argyle Place to Hamilton Avenue
  • South Argyle Place From Hamilton Avenue to North Argyle Place
  • Spring Grove Avenue From Elmore Street to Crawford Avenue (*Started July 5)
  • William P. Dooley By Pass From Elmore Street to Spring Grove Avenue

0 Comments



Leave a Reply.

    City of Cincinnati

    Improve your commute. Use RoadmapCincy, the City of Cincinnati's official site for transportation-related construction projects.

    Follow RoadmapCincy for tips on getting in and out of Downtown and Over-the-Rhine as construction continues to boom. 

    ​​Get there. Here's how.

    Categories

    All
    Downtown Construction
    Streetcar

    Archives

    February 2020
    July 2019
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014

    RSS Feed

©2014 City of Cincinnati
For Streetcar construction updates, please visit CincinnatiStreetcar.com
Picture