​Preparing to Pave in Avondale, Corryville and Northside 

11/8/2016

0 Comments

 
Picture
Thursday, Nov. 3, 2016
Media Contact: Ursula Miller
ursula.miller@cincinnati-oh.gov
513-352-3417
 
CINCINNATI – Crews doing $9.9 million in rehabilitation work to city streets are preparing to pave and finish the three remaining target neighborhoods.

Crews recently finished full-depth, curb and driveway repairs, and are now adjusting utility castings in Avondale, Corryville and Northside in preparation for final paving this month in those neighborhoods. Except for minor finish work, rehab is complete in five of the eight initial target neighborhoods of Kennedy Heights, Madisonville, Pleasant Ridge, Evanston and North Avondale.

This rehab project is funded as part of the city’s Capital Acceleration Plan. It covers approximately 37 lane miles in eight neighborhoods in 2016. Combined with the annual street improvement program, outside grants and CAP, the city is investing approximately $172 million to rehabilitate or resurface more than half its 2,936 total lane miles in all 52 neighborhoods by June 30, 2021.

Please see below for a complete list of streets that have undergone rehabilitation in 2016.

The type of work varied based on the condition of each street but generally included:
  • Grinding and leveling
  • Replacing curbs and curb ramps
  • Repairing driveway aprons and sidewalks, as required
  • Adjusting utility castings to grade
  • Final surface coat of new pavement
  • Line striping
 
On-street parking will be prohibited, as needed, to accommodate crews for paving. Signs will be posted in advance to allow motorists time to find alternate parking options. In most cases, these temporary restrictions will be in place for less than 24 hours and a street will be reopened by 6:00 p.m. Violators will be towed per city ordinance. 
 
A final update on the rehab project will be sent later this month.

Cincinnati Streets Included in 2016 Street Rehabilitation Project
 
Kennedy Heights, Madisonville and Pleasant Ridge (All roads finished by Sept. 30 except for minor finish work.)

  • Carpathia Street from East Terminus to Lester Road
  • Cypress Way from South Terminus  to Montgomery Road
  • Davenant Avenue from East Terminus  to Kinoll Avenue
  • Fairway Drive from Montgomery Road  to Langdon Farm Road
  • Highland Drive from Lester Road  to Corporation Line
  • Hurd Avenue from Plainville Road  to West Terminus
  • Iberis Avenue from Hedge Avenue  to Red Bank Road
  • Indian Mound Avenue from Corporation Line  to Cypress Way
  • Islington Avenue from Watterson Street  to La Crosse Avenue
  • Kincaid Lane from South Terminus  to Kincaid Road
  • La Crosse Avenue from Murray Road  to North Terminus
  • Mapleleaf Avenue from Ridge Avenue  to Lester Road
  • Marmion Lane from South Terminus  to Douglas Terrace
  • McHugh Place from South Terminus  to Montgomery Road
  • Onondago Avenue from Davenant Avenue  to Congreve Avenue
  • Rex Avenue from South Terminus  to Islington Avenue
  • Solar Vista Place from East Terminus  to Kennedy Avenue
  • Valleyview Avenue from Davenant Avenue  to Aikenside Avenue
  • Verulam Avenue from South Terminus  to Auten Avenue
  • Vinewood Avenue from Corporation Line  to Plainville Road
  • Wiehe Road from Langdon Farm Road  to Corporation Line
 
 
Avondale, Corryville, Evanston and North Avondale (Roads to be finished by Nov. 30 are in bold and noted by asterisk. Others are substantially complete except for various minor finish work.


  • Alaska Court From Glenwood Avenue to North Terminus  (*To finish by Nov. 30)
  • Bonaparte Avenue From Hewitt Avenue to Huron Avenue (Complete)
  • Burnet Avenue From William H Taft Road to Forest Avenue *To finish by Nov. 30)
  • Debbe Lane Reading Road to North Terminus (Complete)
  • Dickson Avenue From Clinton Springs Ave to Mitchell Ave  (Complete)
  • Durrell Avenue From Victory Parkway to Gilbert Avenue (Complete)
  • Forest Avenue From Reading Road Dury Avenue (*To finish by Nov. 30)
  • Glencross Avenue From Wedgewood Avenue to Mitchell Ave (Complete)
  • Graydon Avenue From Hewitt Avenue to Huron Avenue (Complete)
  • Hickman Avenue From Reading Road to Harvey Avenue (*To finish by Nov. 30)
  • Hickory Street From Knott Street to West Terminus (*To finish by Nov. 30)
  • Holloway Avenue From Fairfield Avenue to Montgomery Road (Complete)
  • Holloway Court From South Terminus to Holloway Avenue (Complete)
  • Huron Avenue From Bonaparte Avenue to Fairfield Avenue (Complete)
  • Knott Street From Maple Avenue to Rockdale Avenue (*To finish by Nov. 30)
  • Lenox Lane From South Terminus to Redway Avenue (Complete)
  • Maple Avenue From Reading Road to Harvey Avenue (*To finish by Nov. 30)
  • Marion Avenue From Winding Way to North Terminus (Complete)
  • Red Bud Place From Red Bud Avenue to Rose Hill Avenue (Complete)
  • Spokane Avenue From Hewitt Avenue to Huron Avenue (Complete)
  • Vernon Place From Oak Street to Martin Luther King Jr. Drive (*To finish by Nov. 30)
  • Vernon Place From Vernon Place to North Terminus  (*To finish by Nov. 30)
  • Vine Vista Place From Clinton Springs Avenue to North Terminus (Complete)
  • Warwick  Avenue From Clinton Springs Avenue to Mitchell Avenue (Complete)
Northside  (Work scheduled to be finished by Dec. 1.)
  • Cosby Street From Spring Grove Avenue to Hamilton Avenue
  • Mad Anthony Street From William P Dooley By Pass to Spring Grove Avenue
  • North Argyle Place From South Argyle Place to Hamilton Avenue
  • South Argyle Place From Hamilton Avenue to North Argyle Place
  • Spring Grove Avenue From Elmore Street to Crawford Avenue
  • William P. Dooley By Pass From Elmore Street to Spring Grove Avenue
 
Central Business District (To finish by Dec. 1, 2016)
  • Rusconi Place From Shillito Place to Sixth Street
  • Shillito Place From Race Street to Rusconi Place
 
Oakley (To finish by Dec. 1, 2016)
  • Brotherton Road From Madison Road to Terminus
 
 



0 Comments



Leave a Reply.

    City of Cincinnati

    Improve your commute. Use RoadmapCincy, the City of Cincinnati's official site for transportation-related construction projects.

    Follow RoadmapCincy for tips on getting in and out of Downtown and Over-the-Rhine as construction continues to boom. 

    ​​Get there. Here's how.

    Categories

    All
    Downtown Construction
    Streetcar

    Archives

    February 2020
    July 2019
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014

    RSS Feed

©2014 City of Cincinnati
For Streetcar construction updates, please visit CincinnatiStreetcar.com
Picture