Busy Start to Spring Construction Season Along the Riverfront & Downtown 

2/27/2015

0 Comments

 
Picture
Feb. 27, 2015
MEDIA CONTACT: Ursula Miller, ursula.miller@cincinnati-oh.gov, or 513-352-3417

CINCINNATI –
Construction crews will be especially busy along the riverfront and in downtown’s Central Business District in March as work progresses on several high-profile projects that include the Cincinnati Streetcar, The Banks Phase II apartments, General Electric’s U.S. Global Operations Center, Carol Ann’s Carousel and Smale Riverfront Park. In addition, both the Cincinnati Reds and Cincinnati Bengals are installing new scoreboards and several major events are taking place at U.S. Bank Arena and along the riverfront.

The work will require street and pedestrian detours throughout the month. Please see the map below for details. 











































To help maintain traffic flow, Cincinnati police will operate signals at key intersections during morning and afternoon rush hours while streetcar track is installed and for special events. Arrow boards and instructional signage will be posted. The city also will share updated detour information and guidance on how best to navigate around construction sites.

Motorists and pedestrians are encouraged to plan ahead before visiting the area, to use caution and check @RoadmapCincy for daily updates on conditions.

“There is an economic boom occurring in our urban core, which is exciting for the whole city," said City Manager Harry Black. “We also recognize construction in these high-traffic areas can create challenges for motorists and pedestrians.”

Following are the highlights of what motorists and pedestrians can expect in March. Additional details on lane restrictions, road closures and detours will be provided closer to the effective dates for all work:

  • March 2 – March 6: Preparation for streetcar track installation. Walnut between Second and Freedom Way closed to through traffic 9 a.m. to 4 p.m. Local access maintained.
  • March 2 – 31: Concrete pours scheduled to take place on various dates at The Banks Phase II and G.E. on Freedom Way between Race and Rosa Parks streets.
  • March 2 – 17: Crane operators install new signage and scoreboard at Great American Ballpark. 
  • March 7: CinciCARTic Race takes place on sidewalks throughout downtown starting and ending at Fountain Square, stretching between Sawyer Point and Henry Street in Over-the-Rhine.
  • March 5 – March 8: Circus at U.S. Bank Arena. Lane restrictions and closures in place March 2 – March 9.
  • March 6 – 9: Track for the streetcar to be installed on Walnut Street through the intersection at Fifth Street. 
  • March 13 – 14; 25, 27, 28 and 31: Cincinnati Cyclones at U.S. Bank Arena.
  • March 14-15: St. Patrick’s Day Parade and Heart Mini Marathon take place downtown.
  • March 16 – March 27: Track for the streetcar to be installed on Walnut where it curves into Second Street. 
  • March 21: Eric Church concert at U.S. Bank Arena.
  • March 1 – 31: Ongoing underground utility improvements on Main Street at Third north to Central Parkway. 
Please note:

  • Access to the Central Riverfront Garage will be maintained at all times. See attached map for details.
  • Work on a new scoreboard at Paul Brown Stadium is tentatively scheduled to begin this spring but the exact timeline is under review. 
  • In addition, progress continues on Smale Riverfront Park and Carol Ann’s Carousel but there are no current plans for work that would affect motorists in March.


banks_combination_release_final2.27.15.pdf
File Size: 192 kb
File Type: pdf
Download File

0 Comments

Eastbound East Court Street Reopens By March 2;Power Substation To Be Delivered Tomorrow to Metro’sTransit Center

2/19/2015

0 Comments

 
Feb. 19, 2015
MEDIA CONTACT: Ursula Miller, ursula.miller@cincinnati-oh.gov, or 513-352-3417

CINCINNATI – The closure of eastbound East Court Street between Walnut and Main has been extended to Monday, March 2, due to this week’s extreme cold and snow. The one-block stretch, closed since Feb. 13, to allow crews to install conduit to power the Cincinnati Streetcar, had been scheduled to reopen Monday, Feb. 23.

Main Street remains open while work is under way but has lane restrictions between Ninth and East Court streets. Motorists traveling on Walnut are being detoured east on Seventh Street and north on Main.


Pedestrian access on the south side of East Court has been maintained, as well as all crosswalks. On-street parking on the south side is prohibited during the closure. Parking on the north side remains open.


Detour signage is posted.


Other streetcar work

A power substation for the streetcar will be delivered by tractor-trailer to Metro’s Transit Center mid-morning tomorrow, Friday, Feb. 20. Motorists may be temporarily stopped after the tractor-trailer exits I-275 and travels with police escort via Montgomery Road to Reading to Eggleston to its destination on Pete Rose Way.

This is the last of four substations to be delivered for the streetcar. The substations power the streetcar along its 3.6-mile route. One is located at the streetcar’s maintenance and operations facility on the north end of the route in Over-the-Rhine, one is in the parking lot at Findlay Market at Race and Findlay streets and the other is at Court and Walnut. 



court_street_conduit_update_and_tpss2.19.15.pdf
File Size: 176 kb
File Type: pdf
Download File

0 Comments

EB East Court Street to Close Feb. 13 - 23 for Installation of Conduit 

2/10/2015

0 Comments

 
FOR IMMEDIATE RELEASE
Feb. 10, 2015
MEDIA CONTACT: Ursula Miller, ursula.miller@cincinnati-oh.gov, or 513-352-3417

CINCINNATI – Eastbound East Court Street between Walnut and Main will be closed for 10 days beginning at 6:00 p.m. Friday, Feb. 13, so crews can dig a trench and install conduit to power the Cincinnati Streetcar. The conduit will carry cables linking the streetcar track on Main Street to the traction power substation on East Court at Walnut.

Main Street will remain open while work is under way but will have lane restrictions between Ninth and East Court streets. Motorists traveling on Walnut will be detoured east on Seventh Street and north on Main.

Pedestrian access on the south side of East Court will be maintained, as well as all crosswalks. On-street parking on the south side will be prohibited during the closure. Parking on the north side will remain open.


Detour signage will be posted.


This stretch of East Court Street is scheduled to reopen by 6:00 a.m. Monday, Feb. 23.


eb_court_street_conduit_installation2.10.15.pdf
File Size: 167 kb
File Type: pdf
Download File

0 Comments

EB East Court Street to Close Tomorrow for Conduit Prep Work

2/6/2015

0 Comments

 
Feb. 6, 2015
MEDIA CONTACT: Ursula Miller, ursula.miller@cincinnati-oh.gov, or 513-352-3417

CINCINNATI – Eastbound East Court Street between Walnut and Main will be closed tomorrow, Saturday, Feb. 7, from 8:00 a.m. to 4:00 p.m. so crews can prepare the area for the installation of conduit to power the Cincinnati Streetcar.

Main Street will remain open but will have lane restrictions between Ninth and East Court streets. Motorists traveling on Walnut will be detoured east on Seventh Street and north on Main.


Pedestrian access on the south side of East Court will be maintained, as well as all crosswalks. On-street parking will be prohibited during the closure.

Detour signage will be posted.


Note:
The same stretch of East Court Street will be closed from 6:00 p.m. Friday, Feb 13, to 6:00 a.m. Monday, Feb. 23, so crews can install the conduit, which protects the electric wiring between existing Duke Energy lines and the streetcar’s transaction power substation on Walnut and Court streets. More information will be provided in another news release next week.


Other streetcar work
All lanes of Race Street as well as Elder Street between Race and Goose Alley in Over-the-Rhine are scheduled to reopen Monday, Feb. 9. This stretch of Elder has been closed since Jan. 26 while crews installed spur track for the streetcar.



eb_court_street_conduit_prep2.6.15.pdf
File Size: 166 kb
File Type: pdf
Download File

0 Comments

    City of Cincinnati

    Improve your commute. Use RoadmapCincy, the City of Cincinnati's official site for transportation-related construction projects.

    Follow RoadmapCincy for tips on getting in and out of Downtown and Over-the-Rhine as construction continues to boom. 

    ​​Get there. Here's how.

    Categories

    All
    Downtown Construction
    Streetcar

    Archives

    March 2021
    February 2020
    July 2019
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014

    RSS Feed

©2014 City of Cincinnati
For more information, visit: cincinnati-oh.gov/dote 
Picture