First Multi-Vehicle Streetcar Tests to Take Place in CBD & OTR Monday; Short-Circuit Tests Sunday Prep for Monday, Will Produce Audible ‘Boom’ Sounds 

12/4/2015

0 Comments

 
Picture
FOR IMMEDIATE RELEASE
Friday, Dec. 4, 2015
MEDIA CONTACT: Rocky Merz, 513-352-5358 or Ursula Miller, 513-352-3417

CINCINNATI  –  Crews for the Cincinnati Streetcar will conduct the system’s first multi-vehicle tests along the full 3.6-mile route Monday, Dec. 7, starting on Race Street in Over-the-Rhine at approximately 9:30 a.m.

The tests will take place in four separate locations along the route in Over-the-Rhine and the Central Business District. 

The first test will be on Race Street, the next on Walnut and then along two stretches of Main Street, at the southern end of the route near The Banks and another farther north on Main between Central Parkway and Court Street.
​
Police will escort the streetcars as they travel the route to help manage traffic. There will be brief, rolling closures in the streetcar lane and at adjacent intersections as crews prep and conduct each test. Motorists traveling in these areas should expect periodic delays.

The two streetcars will be positioned in tandem and will accelerate simultaneously up to 25 miles per hour at each location as part of the tests. The tests will be conducted at least twice in each location.

This round of tests will help determine how much power is needed per substation when two streetcars are running at the same time and how well all aspects of the system are working together. Crews already have run tests to check track alignment and clearances, as well as overhead wire and substation performance.

In addition, as preparation for Monday, crews will conduct short-circuit tests at each of the four substations on Sunday morning, Dec. 6.

The short-circuit tests, by design, will cause intermittent, audible ‘boom’ sounds within earshot of each substation as current levels fluctuate. Residents and visitors should know that the sounds are expected and do not pose a danger to public safety.

The remaining three streetcars in the five-vehicle fleet are scheduled to be delivered in January and February. Crews will continue live-power testing until pausing for the holidays on Dec. 17. Testing will resume in early January.
​
Passenger service for the streetcar is expected to begin in September 2016.


0 Comments



Leave a Reply.

    City of Cincinnati

    Improve your commute. Follow Roadmap Cincy for tips on getting in and out of Downtown and Over-the-Rhine during the construction boom. Get there. Here's how.

    Categories

    All
    Downtown Construction
    Streetcar

    Archives

    July 2019
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014

    RSS Feed

©2014 City of Cincinnati
For Streetcar construction updates, please visit CincinnatiStreetcar.com
Picture