- Preparation for exterior demolition begins on Elm Street skywalk Monday, March 29
- Stripping exterior of skywalk where it meets the convention center
- Set up temporary barriers and fencing around skywalk
- Heavier demolition of skywalk expected to begin Wednesday, March 31
- Expected completion: April 9
- Interior abatement continues in the south building
- Final reviews/inspections of the completed abatement and waste removal throughout the north tower in its entirety and at the south tower from level four to the top
TRAFFIC IMPACT
- Elm Street between 5th and 6th Street closed until June 20222
- Sidewalk along east side of the convention center closed until completion of Elm Street skywalk demolition
- Sidewalk expected to reopen by April 9
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries
UPCOMING WORK
- North podium demolition expected to begin in mid to late spring