- North Tower:
- Demolition of the 31st floor exterior and interior concrete walls and windows.
- Demolition of the 31st floor concrete slab.
- South Tower:
- Begin interior demolition of top floor (21st floor)
- Upcoming Next Week: Begin structural demolition of the rooftop concrete deck Sept. 22.
- Begin interior demolition of top floor (21st floor)
RECENTLY COMPLETED
- Demolition of annex building completed Sept. 2.
- North Tower: Completed demolition of the 32nd floor concrete walls.
- Completed demolition of the 32nd floor concrete slab on metal deck and began demolition of the 32nd floor structural steel beams and columns.
- Completed debris removal from the south podium.
- Preparation for the start of the south tower demolition.
- Met with Fire Department (Heavy Rescue) on site to review the fully installed safety & protection systems and review progress and conditions on site.
CURRENT TRAFFIC AND PEDESTRIAN IMPACTS
- Elm Street between 5th and 6th streets remains closed through June of next year: 2022.
- Detour: Motorists traveling north on Elm are being detoured west at Fourth and east at Fifth.
- Sidewalk along Elm Street between 5th and 6th adjacent to the convention center closed due to tower demo.
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries