DEMOLITION DETAILS
  • Demolition of the middle podium between the north and south towers continues
  • Begin prep for south podium demolition
  • Interior non-structural demolition in north tower continues on floor 20, and starting on floors 19 and 18
  • Underground gas line work on 5th Street, May 3 - May 5 between 8 a.m. and 3 p.m. daily

TRAFFIC IMPACT 
  • 5th Street: Additional lane closures, as needed, for underground gas line work
    • Flaggers on site to help manage traffic, including entrance and exit at the Hyatt Hotel
  • Elm Street between 5th and 6th streets remains closed through  June 20222
ACCESS ​
  • Sidewalk along Elm Street between 5th and 6th streets open
    • Expected to remain open until Memorial Day unless there is an unexpected public safety issue​
  • Public access to convention center via entrance at the corner of 5th and Elm
  • ADA ramp also open at 5th and Elm
  • Dock on on north side of convention center along 6th Street open for deliveries 

Recent photos

0 Comments



Leave a Reply.

    overview

    Demolition of the former Millennium Hotel complex is using cranes and other heavy equipment to clear the site for future redevelopment.

    Site includes a 34-story tower and five-story annex building to the north along Sixth Street and a 24-story tower to the south along Fifth, as well as a skywalk over Sixth and a skywalk that connects to the Duke Energy Convention Center over Elm.

    Expected Completion:
    June 2022 

    General Contractor:
    Turner Construction Co.

    Demolition Contractor: O'Rourke Wreckng Co.

    Building Owner:
    The Port -  Greater Cincinnati

    Inspection Manager:
    City of Cincinnati

    Archives

    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021

©2014 City of Cincinnati
For more information, visit: cincinnati-oh.gov/dote 
Picture