- Demolition of the middle podium between the north and south towers continues
- Begin prep for south podium demolition
- Interior non-structural demolition in north tower continues on floor 20, and starting on floors 19 and 18
- Underground gas line work on 5th Street, May 3 - May 5 between 8 a.m. and 3 p.m. daily
- 5th Street: Additional lane closures, as needed, for underground gas line work
- Flaggers on site to help manage traffic, including entrance and exit at the Hyatt Hotel
- Elm Street between 5th and 6th streets remains closed through June 20222
- Sidewalk along Elm Street between 5th and 6th streets open
- Expected to remain open until Memorial Day unless there is an unexpected public safety issue
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries