- Continue installation of mast climbers at the south and west side of the north tower
- Continue installation of personnel hoist for the north tower
- Complete demolition of south podium adjacent to 84.51 building
UPCOMING WORK
- Demolition of north tower to begin late the week of July 12
- Sidewalk along Elm Street between 5th and 6th adjacent to the convention center will close once demolition begins
RECENT WORK: WEEK OF JUNE 28
- Continued preparation of the south tower dump chute for demolition debris
- Continued installation of mast climbers at the south and west sides of the north tower
- Began installation of personnel hoist for north tower
- Energized temporary electric service
- Completed electric inspections for temporary service
CURRENT TRAFFIC IMPACT
- Elm Street between 5th and 6th streets remains closed through June of next year: 2022
- Sidewalk along Elm Street between 5th and 6th streets now closed
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries