Aug. 16 - aug. 20

8/13/2021

0 Comments

 
THIS WEEK

  • Mass demolition of annex building on Sixth Street at Elm begins Monday, Aug. 16. Expected completion by Friday, Sept. 3 or sooner.
    • ACCESS: Sixth Street closed between Elm and Race. Motorists heading west on Sixth will be detoured south at Race Street and west again at Fourth. 
  • Demolition of north tower under way.
    • ACCESS: Sidewalk along Elm Street between 5th and 6th adjacent to the convention center now closed due to tower demo.
  • Installation of mast climbers nearing completion on the south tower. Demolition expected to begin in late August. Check back for updates.
0 Comments



Leave a Reply.

    overview

    Demolition of the former Millennium Hotel complex is using cranes and other heavy equipment to clear the site for future redevelopment.

    Site includes a 34-story tower and five-story annex building to the north along Sixth Street and a 24-story tower to the south along Fifth, as well as a skywalk over Sixth and a skywalk that connects to the Duke Energy Convention Center over Elm.

    Expected Completion:
    June 2022 

    General Contractor:
    Turner Construction Co.

    Demolition Contractor: O'Rourke Wreckng Co.

    Building Owner:
    The Port -  Greater Cincinnati

    Inspection Manager:
    City of Cincinnati

    Archives

    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021

©2014 City of Cincinnati
For more information, visit: cincinnati-oh.gov/dote 
Picture