JULY 19 - JULY 23

7/19/2021

0 Comments

 
THIS WEEK
  • Continue building personnel hoist for the north tower
  • Complete installation of mast climbers at the north tower
  • Complete installation of personnel hoist for the north tower
  • Begin selective demolition of the north tower penthouse once prep finished; target is ate this week
  • Continue installation of mast climbers at the south tower
  • Begin installation of the south tower personnel hoist
  • Complete selective demolition of the south tower penthouse

UPCOMING WORK
  • Mass demolition of Annex Building on Sixth Street at Elm may begin as soon as Monday, July 26
  • Demolition of north tower may also begin as soon as Monday, July 26
    • Sidewalk along Elm Street between 5th and 6th adjacent to the convention center will close once demolition  begins
  • South tower demolition expected to begin in late August. 

RECENT WORK: JULY 2 - July 16
  • Completed mass demolition of south podium
  • Completed preparation of south tower dump chute, which is being used for removal of demolition debris from upper floors
  • Began demolition of south tower penthouse
  • Began installation of south tower mast climbers
  • Nearly completed installation of mast climbers for the north tower
  • Nearly completed installation of personnel hoist for north tower

CURRENT TRAFFIC IMPACT 
  • Elm Street between 5th and 6th streets remains closed through June of next year: 2022
ACCESS ​
  • Public access to convention center via entrance at the corner of 5th and Elm
  • ADA ramp also open at 5th and Elm
  • Dock on on north side of convention center along 6th Street open for deliveries 
0 Comments

JUly 5 - JULY 9

7/7/2021

0 Comments

 
THIS WEEK
  • Continue installation of mast climbers at the south and west side of the north tower
  • Continue installation of personnel hoist for the north tower
  • Complete demolition of south podium adjacent to 84.51 building

UPCOMING WORK

  • Demolition of north tower to begin late the week of July 12
  • Sidewalk along Elm Street between 5th and 6th adjacent to the convention center will close once demolition  begins

RECENT WORK: WEEK OF JUNE 28

  • Continued preparation of the south tower dump chute for demolition debris
  • Continued installation of mast climbers at the south and west sides of the north tower
  • Began installation of personnel hoist for north tower
  • Energized temporary electric service
  • Completed electric inspections for temporary service

CURRENT TRAFFIC IMPACT 
  • Elm Street between 5th and 6th streets remains closed through June of next year: 2022
ACCESS ​
  • Sidewalk along Elm Street between 5th and 6th streets now closed​
  • Public access to convention center via entrance at the corner of 5th and Elm
  • ADA ramp also open at 5th and Elm
  • Dock on on north side of convention center along 6th Street open for deliveries 



0 Comments

    overview

    Demolition of the former Millennium Hotel complex is using cranes and other heavy equipment to clear the site for future redevelopment.

    Site includes a 34-story tower and five-story annex building to the north along Sixth Street and a 24-story tower to the south along Fifth, as well as a skywalk over Sixth and a skywalk that connects to the Duke Energy Convention Center over Elm.

    Expected Completion:
    June 2022 

    General Contractor:
    Turner Construction Co.

    Demolition Contractor: O'Rourke Wreckng Co.

    Building Owner:
    The Port -  Greater Cincinnati

    Inspection Manager:
    City of Cincinnati

    Archives

    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021

©2014 City of Cincinnati
For more information, visit: cincinnati-oh.gov/dote 
Picture