- Continue building personnel hoist for the north tower
- Complete installation of mast climbers at the north tower
- Complete installation of personnel hoist for the north tower
- Begin selective demolition of the north tower penthouse once prep finished; target is ate this week
- Continue installation of mast climbers at the south tower
- Begin installation of the south tower personnel hoist
- Complete selective demolition of the south tower penthouse
UPCOMING WORK
- Mass demolition of Annex Building on Sixth Street at Elm may begin as soon as Monday, July 26
- Demolition of north tower may also begin as soon as Monday, July 26
- Sidewalk along Elm Street between 5th and 6th adjacent to the convention center will close once demolition begins
- South tower demolition expected to begin in late August.
RECENT WORK: JULY 2 - July 16
- Completed mass demolition of south podium
- Completed preparation of south tower dump chute, which is being used for removal of demolition debris from upper floors
- Began demolition of south tower penthouse
- Began installation of south tower mast climbers
- Nearly completed installation of mast climbers for the north tower
- Nearly completed installation of personnel hoist for north tower
CURRENT TRAFFIC IMPACT
- Elm Street between 5th and 6th streets remains closed through June of next year: 2022
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries