DEMOLITION DETAILS
  • Demolition of the middle podium (between the north and south towers) to continue
  • Expected to complete abatement work at the 3rd floor mechanical room in the south building, which will complete abatement for the project
  • Start installation of temporary electric service board and distribution to the project site
  • North tower strip out / interior non-structural demolition to continue on floor 22
TRAFFIC IMPACT 
  • Elm Street between 5th and 6th streets remains closed through  June 20222
ACCESS ​
  • Sidewalk along Elm Street between 5th and 6th streets open
    • Expected to remain open until Memorial Day unless there is an unexpected public safety issue​
  • Public access to convention center via entrance at the corner of 5th and Elm
  • ADA ramp also open at 5th and Elm
  • Dock on on north side of convention center along 6th Street open for deliveries 
RECENT PHOTOS
Picture
Picture
Picture
Picture
Picture
Picture
Picture
0 Comments



Leave a Reply.

    overview

    Demolition of the former Millennium Hotel complex is using cranes and other heavy equipment to clear the site for future redevelopment.

    Site includes a 34-story tower and five-story annex building to the north along Sixth Street and a 24-story tower to the south along Fifth, as well as a skywalk over Sixth and a skywalk that connects to the Duke Energy Convention Center over Elm.

    Expected Completion:
    June 2022 

    General Contractor:
    Turner Construction Co.

    Demolition Contractor: O'Rourke Wreckng Co.

    Building Owner:
    The Port -  Greater Cincinnati

    Inspection Manager:
    City of Cincinnati

    Archives

    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021

©2014 City of Cincinnati
For more information, visit: cincinnati-oh.gov/dote 
Picture