- Demolition of the middle podium (between the north and south towers) to continue
- Expected to complete abatement work at the 3rd floor mechanical room in the south building, which will complete abatement for the project
- Start installation of temporary electric service board and distribution to the project site
- North tower strip out / interior non-structural demolition to continue on floor 22
- Elm Street between 5th and 6th streets remains closed through June 20222
- Sidewalk along Elm Street between 5th and 6th streets open
- Expected to remain open until Memorial Day unless there is an unexpected public safety issue
- Public access to convention center via entrance at the corner of 5th and Elm
- ADA ramp also open at 5th and Elm
- Dock on on north side of convention center along 6th Street open for deliveries