2020 Street Rehabilitation Downtown, OTR, Queensgate

4/1/2020

0 Comments

 
Update: Aug. 31 - Sept. 4, 2020

Central Business District
  • FIFTH STREET, BROADWAY STREET, PIKE STREET
    • Paving is scheduled to take place beginning Tuesday, Sept. 8, 2020
    • Full access for motorists and pedestrians until paving begins. Check back for updates the week of Sept. 7, 2020. 

​​LOCATION: The following list of streets have been rehabbed as part of this project:

NEIGHBORHOOD               STREET                       FROM                                    TO
CBD/Riverfront                    7th Street Ramp       Gilbert Avenue Viaduct       Broadway
CBD/Riverfront                    Bedinger Street        Eggleston Avenue                 Broadway
CBD/Riverfront                    Egan Alley                  McFarland Street                  4th Street
CBD/Riverfront                    Gano Street               Walnut Street                        Vine Street
CBD/Riverfront                    Garfield Place            Vine Street                             Elm Street
CBD/Riverfront                    George Street            Elm Street                              Plum Street
CBD/Riverfront                    Gilbert Avenue          Court Street                           Gilbert Ave Viaduct
CBD/Riverfront                    Mehring Way             Broadway                               Elm Street
CBD/Riverfront                    Ogden Place               Vine Street                             75' West of Vine Street
CBD/Riverfront                    Oneida Alley               Vine Street                             Race Street
CBD/Riverfront                    Paulding Place           South Terminus                    6th Street
CBD/Riverfront                    Postal Place                4th Street                               Honing Alley
CBD/Riverfront                    Ruth Lyons Lane        6th Street                               7th Street
Over-the-Rhine                    13th Street                  Main Street                            Race Street
Over-the-Rhine                    Clay Street                  Central Parkway                    12th Street
Over-the-Rhine                    Cogswell Alley            Orchard Street                      Plough Alley
Over-the-Rhine                    Goetz Alley                 Orchard Street                       Plough Alley
Over-the-Rhine                    Plough Alley                Cogswell Alley                       Goetz Alley
Pendleton                             Reading Rd Ramps    Elsinore Pl                      Bridges for I-71/Reading Rd
Queensgate                          5th Street Ramp         Central Ave                           6th Street Expy
Queensgate                          6th Street Ramp         Central Ave                           6th Street Expy
Queensgate                          6th Street Ramp         6th Street Expy                     Gest Street
Queensgate                         7th Street Ramp          Bridge Over I-75                   8th Street
Queensgate                          8th Street                     Bridge Over I-75                  8th Street Viaduct
Queensgate                          Dalton Avenue            9th Street                              Hopkins Street
Queensgate                          Freeman Avenue        Mehring Way                        Gest Street
Queensgate                          Gest Street                   3rd Street                             Western RR Overpass
Queensgate                          Linn Street                    Dalton Ave                            Bridge Over Gest St
Queensgate                          Mehring Way               Carr Street                            Harriet Street
Over-the-Rhine                     Liberty St                      Reading Rd                           Dalton Ave
Pendleton                              Liberty Hill                    Highland Ave                       Liberty Street
CBD/Riverfront                     5th Street                    Pike Street                           Main Street
CBD/Riverfront                     Broadway                    4th Street                            Eggleston Avenue
CBD/Riverfront                     Columbia Pkwy           Bridge Over Culvert St      Pike Street
CBD/Riverfront                     Elm Street                    3rd Street                            5th Street
CBD/Riverfront                     Pike Street                   3rd Street                            5th Street

What's Happening

CINCINNATI - The City of Cincinnati is rehabilitating 36 streets and alleys throughout the Central Business District, Over-the-Rhine and Queensgate in 2020. 
Work began Monday, March 2.

Most of the the project is expected to be finished by Nov. 1, 2020. 

The contractor is Prus Construction.

Through traffic generally will be allowed, though there may be intermittent lane closures, as needed, depending on the location. Updates will be posted and the contractor will coordinate with properties to allow for access and deliveries.

For more information, visit: www.cincystreetrehab.com
0 Comments

    Downtown Rehab

    In 2020, the City of Cincinnati will be rehabilitating 36 streets and alleys throughout the Central Business District, Over-the-Rhine and Queensgate.